UK Infrastructure Projects: How Legal Challenges Could Change

Infrastructure Projects

The proposed changes to legal challenges for nationally important infrastructure projects could offer more certainty before construction begins. The proposals place more emphasis on resolving legal, environmental and community concerns during planning.

In the package announced on 7 September 2026, the government set out plans for Parliament to designate and approve selected infrastructure projects. It also proposed a fixed period for legal challenges. This aims to bring objections forward before developers commit to construction programmes and major investment.

The details will depend on legislation that the government has yet to publish. The government hasn’t confirmed which projects will qualify, how parliamentary approval will work or how long the challenge period will last. Therefore, anyone developing a scheme will need to continue following the current process while these arrangements take shape.

What has been proposed?

Under the proposals, the relevant Secretary of State would identify projects of critical national importance. Parliament would then vote on their designation and final consent. This could give approved schemes greater protection from later legal challenges.

The government first outlined this approach in May 2026 for critical clean energy infrastructure. This included power stations, offshore wind farms and grid connections. Its September announcement extended the proposal to other nationally important projects, although the sectors and qualifying criteria remain undefined.

Alongside parliamentary approval, the proposed fixed challenge window would give people a set period to raise potential grounds for legal challenge. The intention is to address concerns earlier and reduce the uncertainty that can arise when claims follow consent.

The earlier policy paper on infrastructure judicial review proposed requiring courts to refuse permission for certain challenges. This would apply where no one had raised the issue during the consenting process or challenge window. Both proposals need more detail and primary legislation before anyone can fully assess their effects.

They follow changes to judicial review in the Planning and Infrastructure Act 2025. These concern National Policy Statements and Development Consent Order decisions. Under those changes, disputed applications for permission would proceed to an oral High Court hearing. If the court refuses permission and finds a claim totally without merit, the claimant would lose the right to appeal. This would prevent an appeal to the Court of Appeal. These provisions require commencement regulations to take effect before they apply.

What could this mean for infrastructure projects?

The government estimates that judicial review challenges typically delay nationally important infrastructure projects by around 18 months. It points to Sizewell C, where two unsuccessful challenges contributed to delays.

For those responsible for delivering a scheme, uncertainty over consent can affect finance, land agreements, procurement and the timing of construction. Resolving challenges earlier could make it easier to commit to arrangements. It could also give suppliers and contractors greater confidence when planning their work. Much will still depend on the quality of the application and the decisions supporting it. Environmental assessments, consultation records and evidence of policy compliance help explain how a scheme responds to its surroundings. They also show how it addresses the concerns people have raised. Clear records of key decisions would be particularly important if there were less time to raise or respond to a challenge.

The proposals also raise questions about access to justice. Legal reform organisation JUSTICE has questioned the evidence for extending existing judicial review restrictions beyond Nationally Significant Infrastructure Projects. Its response concerns a separate consultation on wider planning decisions and highlights the scrutiny that further restrictions are likely to receive.

For anyone developing an infrastructure scheme, it’s important to prepare a well-supported application and address concerns while the design can still evolve. Planning, environmental and public law advice can help to identify potential weaknesses during design development. This leaves time to explore alternative options or carry out further assessments before submission.

Early engagement with communities and other stakeholders also helps reveal issues that technical studies alone may overlook. A clear record of those discussions can strengthen the evidence supporting an application, particularly when it explains how they informed the proposals.

Environmental statements, assessments of alternative options and decision records should explain how those developing the scheme considered and addressed concerns. Gaps in this evidence could become harder to resolve within a tighter challenge period.

Until the government confirms the legislation and its start date, budgets and programmes should continue to allow for legal challenges and delays. They should also allow for any redesign linked to consent. Schemes already underway will need clarity on whether the new arrangements apply to them.

The proposed reforms could give selected infrastructure projects a more predictable route from consent to construction. Their practical value will depend on how the approval and challenge processes work. It will also depend on how effectively those developing schemes resolve outstanding issues before consent.